 Domain Automation IT
 Project Name Sort Allocation Computer for Zine El Abidine Ben Airport, Enfidha, Tunisia
 Client Vanderlande Industries
 Consultant
 Project Highlights
• Project management, planning and project organization were supplied to the client.
• The functional design specification (FDS) was provided based on tender documents and the requirements discussed during    input collection.
• The commissioning, SAT and training was closed in less than seven days.
• CAT and handover were seamless.
System Configuration
1 HMI : Fox SAC Server Application .
2 Communication Protocol : Ethernet
3 Software : .net + Oracle.
 
  Project Synopsis
 
  SAC is to sort the checked-in baggage at airports to their destination carousels with reference to the passenger baggage data, the flight information and the sort plan. It interfaces with BSM - SITA Bag message Server in London, IX- Information Exchange Server in Istanbul and the Beumer Sorter PLC in Enfidha. Redundant SAC servers are provided for high availability.
  FOX-SAC :
    Project Features
    • Input collection.
    • Project management, planning and project organization were supplied to the client.
    • The functional design specification (FDS) was provided based on tender documents and the requirements discussed during input collection.
    • The functional design specification listed the functional requirements of the system, functional solutions for the requirements, software architecture,    screenshots, hardware configuration and list of open issues.
    • After the open issues were resolved the final copy of FDS was approved by the client.
    • Similarly the interface specification documents were made for the partner interfaces of SAC with IX, Beumer and SITA and were approved by the   client and other partners.
    • The development of software, modular testing, integration testing and load testing was carried out based on FDS and IDS.
    • The FAT document was supplied listing all the test cases.
    • The FAT simulator was developed to simulate all the test cases listed in the FAT document.
    • During FAT, SAC was tested with FAT test case simulator. The FAT with all test cases was closed in two days.
    • The snag list generated during FAT was closed before commissioning started.
    • The commissioning, SAT and training was closed in less than seven days.
    • CAT and handover was seamless.